Economic Highlights
New Delhi, 5 March 2009
Railway Freight
Corridor
LALU’S SHOWMANSHIP
OF TRACK
By Shivaji Sarkar
Gimmickry is something Railway Minister Lalu Prasad Yadav is
well known for. The recent being the proposed eastern freight corridor, which will
be inaugurated for the second time. The
foundation stone for the project was laid by Prime Minister Manmohan Singh in
September 2006 at Ludhiana, months before
elections were held in Punjab.
This time around he has chosen his home State Bihar for a
105-km stretch from near Mughal Sarai to near Sonnagar, a stretch, where a
third railway line largely dedicated to goods traffic already exists. It is
used for transporting coal. The freight projects, both eastern and western are
targeted for completion in 2015 provided the actual work begins now. However,
in all probability these are going to be delayed.
The railway budget for 2006-07 had announced the eastern and
western freight corridor projects, which are expected to cost Rs 28,181 crore
and Rs 16,592 crore respectively. The eastern corridor is proposed to extend
from Ludhiana
to Dankuni, 20 km from the Kolkata port, wherein logically it should have been
extended to Kolkata or the Haldia port.
Lalu is a showman alright. He has a talent to cover up his
tracks. He did so as Bihar’s Chief Minister
and has now extended it to the Indian Railways. So, he doesn’t find anything
wrong in inaugurating the Eastern freight corridor, which was originally to
extend from Ludhiana
to Kolkata, for the second time. All this, despite the fact that an
inauguration is not without a cost to the exchequer. Each such programme has
many overt and hidden costs. It is not merely borne by the railways but many such
costs have to be borne by the State governments, involving areas like transportation,
law and order, security and other paraphernalia.
The freight corridors are no longer a novelty as are being touted.
The corridors have been discussed for many years. In fact the need was felt and
stressed in the eighties. No major project comes up in a day. It is a slow
process, which includes processes, evaluations and cost studies before it is
finally launched.
For a major project like this no single railway minister
could claim credit. In fact, the ministers are clearly incidental as projects
are evolved owing to their functional utility. These are conceived and given
shape by railway officials and engineers often in consultation with State
governments and the Planning Commission.
While the corporate world is well-versed with repeating
shows to launch their products in the metros and major cities, if the same is done
by the Railways it does cause concern. This is so because the Railways are not
as cash rich as its minister would have it projected. In fact, one could say
that the image is engineered, like Lalu being the “management guru”. The Railways
paid Rs 50 lakhs to IIM, Ahmedabad for organizing the minister’s “management”
lecture. A similar exercise is said to have been undertaken with Harvard University as well.
Interestingly, even as Lalu has declared a surplus of Rs
25,000 crore in 2008-09 budget, the Railways is in search of foreign funding
assistance, including a loan from Japan, the World Bank and Asian
Development Bank (ADB). Apparently, it is clarified in this year’s budget that the
actual surplus is not more than Rs 5,000 crore, if the borrowings of Rs 8,000
crore are taken into account.
Barring the Japanese government, no one else has yet made a commitment.
However, Japan has refused to give any assistance for the eastern corridor as
its estimates did not find the corridor a viable project. The reason being that
the returns would be lower as Kolkata being a riverine port is not expected to
generate the amount of traffic required. And thus, the eastern corridor is seen
to have fallen behind the western corridor project, which the Japanese have
decided to support.
This has forced the Railways to take up the small section of
105-km in Bihar from its own resources. The total proposed length of the
corridor is however, 1805 km, but the Railways have chosen to remain silent about
the rest of length. There is much apprehension in the railway ministry that the
105-km section may lock up funds as work would be going in a piecemeal manner.
Till now, the railways had approached the World Bank for
$2.5-billion assistance and the ADB for technical assistance for the eastern
corridor. But no commitment has yet been received. Understandably so, as the world
economy is passing through a critical phase, wherein it is unclear from whether
funding from the two institutions would be forthcoming.
Tokyo has committed to ODA loan of Rs 17045 crores, for the
first phase of the western corridor. This amounts to 62 per cent of the total
cost of Rewari – Vadodara stretch. It is also likely to provide a similar loan
for the second stage of the western corridor, extending to Jawaharlal Nehru
Port Trust in Mumbai. The PM had laid the foundation stone for the project on
October 5, 2006. Sadly, since there has been little progress on construction activity,
the financial tie-ups have not been finalized. Work on both the projects was to begin in the
current financial year, but it is not possible now.
A close look at the projects shows that the first works that
need to be taken up are 54 important bridges over a stretch of 200-km on the
Western corridor, and 105-Km section on the eastern Corridor. While bids for
project management consultancy as well as turn-key contracts in these
sub-projects have reportedly been received, their evaluation is yet to be completed.
It is difficult to understand why are politicians announce such inauguration
jamborees when outcome is clearly doubtful?—INFA
(Copyright, India News and Feature
Alliance)
|